Defect: Delamination
Description: Loss of adhesion to the substrate
Causes: Unsatisfactory surface preparation; incompatible primer or undercoat; substrate or intercoat contamination; excessive cure time between coats
Saturday 3 July 2010
Guideway Survey: 2010 06 28
Defect: Coating Cracking
Description: Deep irregular cracks to the paint film to the steel substrate
Causes: Insufficient drying of films. Excessive film thickness, physical impact, the incompatibility of top and undercoats
Description: Deep irregular cracks to the paint film to the steel substrate
Causes: Insufficient drying of films. Excessive film thickness, physical impact, the incompatibility of top and undercoats
Guideway Survey: 2010 06 28
Defect Found: Pinpoint rusting on the pipe
Description: Rusting at pinholes located in some pipe areas
Causes: Voids in film due to pinholes, voids, holidays: surface profile too high
Description: Rusting at pinholes located in some pipe areas
Causes: Voids in film due to pinholes, voids, holidays: surface profile too high
Guideway Survey: 2010 06 28
Guideway Survey to develop and present a recoating program to repair paint defects
Following presentation of this information, the committee should present a proposed program approach, including target dates, dates for completion of various activities, definition of responsibilities and of the specific objective and scope of work.
These activities shall include the following: coating materials inventory, technical specification approval, meetings, formalization of an inspection program with documentation, safety and health aspects, permits, labor period of time, work methodology and a contractor definition.
These activities shall include the following: coating materials inventory, technical specification approval, meetings, formalization of an inspection program with documentation, safety and health aspects, permits, labor period of time, work methodology and a contractor definition.